Hadeer Desalination Co. is preparing the first risk-identification workshop for a pump-station upgrade. A shortlisted supplier proposes a benchmark showing unusually low equipment failure rates. The summary names no publisher, collection period, or underlying source, and the procurement lead points out that this supplier's last three deliveries were on time. Before the benchmark is used as an input to risk identification, what should the risk manager do?
All 10 free questions with answers and an explanation for every option
What you get
- 500questions in the bankPractise with the answer shown right away, or sit a full timed mock
- 5unitsSplit by the exam syllabus
- 25flashcardsTo lock in terms and definitions
- 35quick review pointsEach unit in a few key lines
Unit map
- 01Risk Strategy and Planning25 questions
- 02Risk Identification27 questions
- 03Risk Analysis26 questions
- 04Risk Response15 questions
- 05Monitor and Close Risks22 questions
Exam facts
PMI Risk Management Professional (PMI-RMP) — Number of questions: 115 questions. Exam time: 150 minutes. Pass mark: PMI does not publish a fixed percentage pass mark. Calculator: On-screen calculator. Exam fee: Fees depend on region and PMI membership; check the amount in your PMI application. Source: Project Management Institute (PMI) (Last verified: 2026-11-04). Question bank: A site supplementary practice session of 115 questions in 150 minutes with a result for every unit, plus 500 explained questions across 5 units, every option explained, a review of your mistakes, and two ways to practise: see the answer right away, or sit a full timed mock. Free questions: a 10-question diagnostic test covering the main units, no sign-up; at the end you get your score and your weakest units.
- Exam language
- English or Arabic or English
- Number of questions
- 115 questions Source
- Exam time
- 150 minutes Source
- Pass mark
- PMI does not publish a fixed percentage pass mark. Source
- Calculator
- On-screen calculator Source
- Exam fee
- Fees depend on region and PMI membership; check the amount in your PMI application. Source
- Retakes
- Up to three attempts within the one-year eligibility period; after three failures, wait one year from the last attempt before reapplying. Source
- Validity
- Maintain certification through the three-year renewal cycle; PMI requires 30 PDUs per cycle. Source
Last verified: 2026-11-04
Where other sources differ
- The certification exam includes single-answer and multiple-answer questions. This bank provides single-answer supplementary practice, not a complete replica of the exam.
How to register
- Check the eligibility route for your education and project risk management experience on PMI’s website.
- Complete the required risk management education and submit your experience and education records.
- After approval, pay the exam fee and schedule a testing-centre or online-proctored appointment.
Exam body
Project Management Institute (PMI): Official website: Project Management Institute (PMI)
Study guides
Frequently asked questions
How long is the PMI-RMP exam?
The exam has 115 questions and allows 150 minutes. Fifteen questions are unscored pretest items.
Can I try PMI-RMP questions for free?
Yes. Free questions: a 10-question diagnostic test covering the main units, no sign-up; at the end you get your score and your weakest units. The free practice test page lists the same questions with answers and an explanation for every option. The rest of the questions and the full mock exams come with a pass from SAR 26.
What makes this PMI-RMP question bank different?
Question bank: A site supplementary practice session of 115 questions in 150 minutes with a result for every unit, plus 500 explained questions across 5 units, every option explained, a review of your mistakes, and two ways to practise: see the answer right away, or sit a full timed mock. Every question is reviewed and referenced, ready to practise on your phone. Try the free questions and read the explanations before buying full access.
Which languages are available?
PMI lists English, Arabic and Simplified Chinese. This practice bank provides English and Arabic.
Does this practice reproduce every exam format?
No. These are single-answer practice questions across the five risk domains; the certification exam also includes multiple-answer items.
What experience and education do I need?
PMI lists three routes: secondary education with 36 months of project risk experience and 40 education hours; a bachelor’s degree or higher with 24 months and 30 hours; or a GAC-accredited degree with 12 months and 30 hours. Experience must be within the last five years. Check the full eligibility conditions before applying.
Is this an official site, and how do I pay?
It is an independent site, not part of Qiyas or any government body, and every question is reviewed before it is published. You pay once, with no automatic renewal, through Waffo Pancake (the merchant of record) by Visa, Mastercard, Apple Pay or Google Pay, and your statement shows "WAFFO". If you were charged twice or the pass did not open, email support@saudiexams.com.
Study material sample: Risk Strategy and Planning
Summary
Strategy makes risk decisions consistent before individual risks are ranked. Establish the evidence base, project context, acceptable exposure, roles and review rules. A sponsor’s enthusiasm does not replace an agreed threshold or a mandatory constraint.
What the exam focuses on
- Review historical records for relevance and provenance. A similar project is useful evidence only where its conditions are comparable. Assign specialist document analysis to people with the relevant expertise.
- Assess organizational assets, environmental factors and lifecycle. In a hybrid project, review risks at the decision points used by each component rather than imposing one calendar without analysis.
Common traps
- Copying a prior plan without testing its assumptions.
- Treating high appetite as permission to ignore a mandatory constraint.
- Measuring success only by the number of risks logged.
Try the flashcards
Tap a card to see the answer
What is the first test of a historical benchmark?
Its source, collection conditions and relevance to this project.
Does a risk category imply priority?
No. Categorization and prioritization answer different questions.
How do appetite and thresholds relate?
Project thresholds translate organizational willingness into usable decision boundaries.
What distinguishes an RBS from a responsibility matrix?
An RBS organizes risk categories; a responsibility matrix assigns roles.
What should a useful risk metric support?
A relevant decision or assessment of effectiveness, with a clear and consistent basis.
Why you can trust these questions
- Published questions: 500. We reviewed every one before publishing it: the answer, the explanation of each option and the source.
- Exam facts last checked against the organiser’s website: 2026-11-04. We check them again every three months and two weeks before each test.
- Found a mistake? Tap "Report an error" under any question in the practice area, or email us at support@saudiexams.com
- Independent website. Not affiliated with ETEC (Qiyas), the Financial Academy or any government body.