Try the questions in the test above first, then open each one here to see the correct answer and why every other option is wrong.
01A farmer fences a rectangular field on three sides only; the fourth side is an existing wall. With 80 m of fence, what is the largest possible area?
Practice question Unit: Mathematics
A800 m² ✓ Correct answer
Correct: width x and length 80-2x give A=x(80-2x); A'=80-4x=0 gives x = 20, length 40 m, so A = 800 m².
B400 m²
Assumes a 20 m × 20 m square, i.e. all four sides fenced.
C1600 m²
Takes both length and width as 40 m, which would need 120 m of fence.
D600 m²
Corresponds to 10 m × 60 m; a feasible area but not the maximum.
Reference: SCE-Qiyas Engineering Fundamentals Exam, General Engineering Standards (2014), Topic T1: Mathematics, indicator GE-T1-01; standard formula: التحسين بجعل المشتقة صفرًا
Ask a friend
02Machine A makes 60% of the parts with a 2% defect rate, and machine B makes 40% with a 5% defect rate. A part is picked at random and found defective. What is the probability it came from machine B?
Practice question Unit: Probability and Statistics
A0.625 ✓ Correct answer
By Bayes' rule: 0.4 \times 0.05 / (0.6 \times 0.02 + 0.4 \times 0.05) = 0.020 / 0.032 = 0.625.
B0.375
This is the probability that the defective part came from machine A, the complement of what is asked.
C0.400
This is the prior probability of machine B and ignores the information that the part is defective.
D0.032
This is the overall probability that a part is defective (the denominator), not the probability of its source.
Reference: SCE-Qiyas Engineering Fundamentals Exam, General Engineering Standards (2014), Topic T2: Probability and Statistics, indicator GE-T2-02; standard formula: Bayes' rule: P(B \mid D) = P(D \mid B)P(B) / P(D)
Ask a friend
03A 2.5 GB file is downloaded over a link with a steady throughput of 20 Mbit/s. Taking 1 GB = 1000 MB and 1 byte = 8 bits, the download time is approximately:
Practice question Unit: Computer Literacy
A1000 s ✓ Correct answer
2.5\times1000\times8 = 20000 Mbit, then 20000/20 = 1000 s.
B8 s
It comes from dividing 20 by 2.5 without converting units, which does not represent a time.
C125 s
It results from skipping the byte-to-bit conversion: 2500 MB ÷ 20 = 125 s, whereas the correct time is 8 times larger.
D2500 s
It equals the file size in megabytes and ignores the transfer rate entirely.
Reference: SCE-Qiyas Engineering Fundamentals Exam, General Engineering Standards (2014), Topic T3: Computer Literacy, indicator GE-T3-01; standard formula: time = size (bit) / rate (bit/s)
Ask a friend
04A simply supported beam of span 5 m carries a uniformly distributed load of 10 kN/m over its full length plus a 20 kN point load at 2 m from support A. What is the vertical reaction at B?
Practice question Unit: Statics and Dynamics
A37 kN
This is the reaction at A (total load 70 kN minus 33 kN).
B35 kN
This is half the total load, which is wrong because the point load is not at mid-span.
C25 kN
This is the share from the distributed load alone, ignoring the point load.
D33 kN ✓ Correct answer
Moments about A: R_B \times 5 = 50 \times 2.5 + 20 \times 2 = 165, so R_B = 33 kN.
Reference: SCE-Qiyas Engineering Fundamentals Exam, General Engineering Standards (2014), Topic T4: Statics and Dynamics, indicator GE-T4-01
Ask a friend
05When \mathrm{Al + HCl \rightarrow AlCl_3 + H_2} is balanced with the smallest whole numbers, what is the sum of the coefficients?
Practice question Unit: Chemistry
A12
Coefficients such as 2, 5, 2, 3 or 2, 6, 2, 2 sum to 12 but leave Cl or H unbalanced.
B11
Coefficients such as 2, 6, 2, 1 sum to 11 but leave H unbalanced (6 atoms against 2).
C13 ✓ Correct answer
Correct: \mathrm{2Al + 6HCl \rightarrow 2AlCl_3 + 3H_2}, and 2 + 6 + 2 + 3 = 13.
D15
Coefficients such as 2, 6, 2, 5 sum to 15 but leave H unbalanced (6 atoms against 10).
Reference: SCE-Qiyas Engineering Fundamentals Exam, General Engineering Standards (2014), Topic T5: Chemistry, indicator GE-T5-03
Ask a friend
06A steel has a yield strength of 250 MPa and a modulus of elasticity of 200 GPa. What is its modulus of resilience?
Practice question Unit: Materials Science and Engineering
A0.156 MJ/m³ ✓ Correct answer
Correct: U_r=\sigma_y^2/(2E)=250^2/(2\times200000)=0.156 MJ/m³.
B0.078 MJ/m³
Wrong: this value comes from dividing by 4E instead of 2E, which is not the correct formula.
C0.313 MJ/m³
Wrong: this value omits the factor 1/2; the area under the elastic curve is a triangle, not a rectangle.
D1.56 MJ/m³
Wrong: this value is ten times too large and comes from a slip in the power of ten during unit conversion.
Reference: SCE-Qiyas Engineering Fundamentals Exam, General Engineering Standards (2014), Topic T8: Materials Science and Engineering, indicator GE-T8-01; standard formula: U_r=\sigma_y^2/(2E)
Ask a friend
07A company has revenue of SAR 1,200,000, cost of goods sold of SAR 700,000, operating expenses of SAR 250,000, and loan interest of SAR 50,000. If tax is 25% of profit before tax, what is net income?
Practice question Unit: Engineering Economics
ASAR 187,500
This taxes profit before deducting interest (250,000 × 0.75); interest is deducted first and tax is computed afterward.
BSAR 200,000
This is profit before tax; the tax has not been deducted.
CSAR 150,000 ✓ Correct answer
Profit before tax = 1,200,000 − 700,000 − 250,000 − 50,000 = 200,000; tax is 50,000, so net income is SAR 150,000.
DSAR 250,000
This is profit after operating expenses but before interest and tax.
Reference: SCE-Qiyas Engineering Fundamentals Exam, General Engineering Standards (2014), Topic T11: Engineering Economics, indicator GE-T11-01
Ask a friend
08A contractor works under a cost-plus-fixed-fee contract. The estimated cost is SAR 750,000, the fixed fee is 10% of the estimated cost, and the actual reimbursable cost is SAR 800,000. What total amount does the owner pay?
Practice question Unit: Project Management
ASAR 880,000
This figure applies the percentage to the actual cost, but the fee here is fixed from the estimated cost.
BSAR 875,000 ✓ Correct answer
The actual cost of 800,000 is reimbursed plus the fixed fee of 75,000 (10% of 750,000), giving 875,000.
CSAR 825,000
This figure adds the estimated cost to the fee and ignores the actual reimbursable cost.
DSAR 800,000
This figure repays only the actual cost and leaves out the contractor's fee.
Reference: SCE-Qiyas Engineering Fundamentals Exam, General Engineering Standards (2014), Topic T12: Project Management, indicator GE-T12-01
Ask a friend
09After issuing construction drawings, an engineer finds a calculation error in his design that reduces the safety margin of a structural member; construction has not started. What is the most appropriate sequence of actions?
Practice question Unit: Ethics and Professionalism
AWait for the next periodic project review and then correct the error if it is confirmed
Delay raises the chance that the flawed design gets built.
BCorrect the error quietly and hand over new drawings without telling any party why they changed
Concealing it keeps affected parties unaware and breaches honesty.
CNotify the owner at once, then correct the design and issue revised drawings replacing the earlier ones ✓ Correct answer
Immediate notification, correction and withdrawal of old drawings is the transparent course that protects the public.
DLeave the design as is because the margin is still positive
A safety margin below the approved design basis cannot be accepted without everyone's knowledge.
Reference: SCE-Qiyas Engineering Fundamentals Exam, General Engineering Standards (2014), Topic T13: Ethics and Professionalism, indicator GE-T13-01
Ask a friend
10An operating rule that always holds: if the cooling pump fails, the alarm sounds. The alarm did not sound during the shift. Which conclusion follows necessarily?
Practice question Unit: General Skills
AThe pump failed but the alarm itself is faulty
This contradicts the rule that the alarm always sounds when the pump fails.
BThe cooling pump did not fail during the shift ✓ Correct answer
Correct: by the contrapositive, had the pump failed the alarm would have sounded.
CThe pump's state cannot be determined from this information
It can be determined: the absence of the certain result (the alarm) rules out the cause (failure).
DThe cooling pump is operating at full efficiency
Not failing does not mean full efficiency; the pump may run poorly without failing.
Reference: SCE-Qiyas Engineering Fundamentals Exam, General Engineering Standards (2014), Topic T14: General Skills, indicator GE-T14-01