حلّ الأسئلة في الاختبار أعلاه أولًا، ثم افتح كل سؤال هنا لترى الإجابة الصحيحة وسبب خطأ كل خيار.
01A customer service center logged 300 complaints in a month across six categories: long waiting (120), wrong invoices (80), service outages (40), poor treatment (30), late activation (20), other (10). Following the Pareto rule (covering about 80% of complaints), how many categories should be addressed first?
سؤال تدريبي الوحدة: تقييم الاحتياجات
أTwo categories: waiting and invoices (200 complaints)
The two categories total 200 of 300, only 66.7%, below the 80% target.
بThree categories: waiting, invoices, and outages (240 complaints) ✓ الإجابة الصحيحة
120 + 80 = 200, i.e. 66.7%; adding service outages brings the total to 240, i.e. 80%.
جFour categories: down to poor treatment (270 complaints)
Three categories already reach 80% (240 of 300); adding a fourth, for 270 or 90%, spreads effort without need.
دOne category: waiting (120 complaints)
One category covers only 40% of the complaints.
المرجع: PMI-PBA Exam Content Outline, Domain 1 Needs Assessment, Task 1 (define or review a business problem or opportunity)
اسأل صديقًا
02An automation initiative at a services company costs SAR 2,000,000 upfront, with annual running costs of SAR 100,000 and annual benefits of SAR 900,000. Ignoring discounting, what is the payback period?
سؤال تدريبي الوحدة: تقييم الاحتياجات
أ2.2 years
This divides the cost by the gross benefit of 900,000 and ignores the annual running cost.
ب2.3 years
This adds 100,000 to the upfront cost and divides by 900,000, treating the running cost as a one-off payment.
ج2.5 years ✓ الإجابة الصحيحة
Net annual cash flow is SAR 800,000 (900,000 minus 100,000), and 2,000,000 divided by 800,000 is 2.5 years.
د2.9 years
This subtracts the running cost twice from the benefit; it should be subtracted once per year.
المرجع: PMI-PBA Exam Content Outline, Domain 1 Needs Assessment, Task 2 (collect and analyze information using valuation tools and techniques to determine the value proposition)
اسأل صديقًا
03A logistics company started an inventory management system project 18 months ago, based on a business case that assumes 15% annual shipment growth. Recent data shows actual growth of only 3%, and the project has spent half its budget. While reviewing the business case before the next analysis phase, what is the most appropriate action?
سؤال تدريبي الوحدة: التخطيط
أTell the sponsor the growth assumption no longer holds and ask for benefits to be re-evaluated before continuing ✓ الإجابة الصحيحة
A key assumption has changed and may weaken the case, so the analyst escalates to the decision maker to re-evaluate benefits before more effort is spent.
بContinue the analysis as planned because half the budget is spent and the decision was approved earlier
Money already spent is a sunk cost and should not decide whether to continue; the project may no longer deliver its benefits.
جUpdate the benefit figures in the business case on their own to reflect the new growth and then inform the project team
The business case belongs to the sponsor, and changing its figures alone undermines transparency and bypasses the approved decision process.
دCut the number of requirements by half to match the budget already spent and what remains
Cutting requirements on spend alone does not address the problem; the question is whether the project is still worthwhile at all.
المرجع: PMI-PBA Exam Content Outline, Domain 2 Planning, Task 1 (review the business case and the project goals and objectives)
اسأل صديقًا
04A bank is preparing for a regulator review in eight months. The regulator will ask for evidence that every regulatory requirement was implemented and tested, and that every feature built has a regulatory or business basis. Which traceability strategy best meets this?
سؤال تدريبي الوحدة: التخطيط
أForward tracing only, from requirements to test cases, because the review focuses on test results
This shows requirements were tested, but cannot reveal a feature that has no regulatory or business basis.
بBackward tracing only, from requirements to their regulatory sources, since the reviewer cares about each requirement's origin
This proves where requirements came from, but not that each one was implemented and tested.
جLinking deliverables to milestones in the project schedule, because the review cares about meeting deadlines
Milestone links belong to schedule management and do not connect regulatory requirements to implementation and testing.
دBidirectional tracing linking clauses to requirements, design and tests, with gap reports ✓ الإجابة الصحيحة
The evidence runs in two directions: every clause must reach a requirement and a test, and every built component must trace to an origin. Bidirectional tracing with gap reports covers both.
المرجع: PMI-PBA Exam Content Outline, Domain 2 Planning, Task 2 (define requirements traceability strategy); SWEBOK Guide V4.0a, Ch. 1 §7.3 Requirements Tracing
اسأل صديقًا
05In an interview, a senior executive says the new customer portal "must be fast." The analyst wants this captured as a usable requirement. What is the best response?
سؤال تدريبي الوحدة: التحليل
أRecord the statement exactly as spoken and move on to the next topic, to respect the executive's time
An untestable statement cannot be verified later and will be interpreted differently by each reader.
بAsk what "fast" means in measurable terms and record the executive as the source ✓ الإجابة الصحيحة
Probing turns a vague wish into a testable requirement, and recording the source keeps it traceable for later questions.
جSet a two-second response time as a reasonable standard and note that the executive approved it
The executive never agreed to that figure; attributing an invented number to the source misrepresents the requirement.
دAsk the development team to define "fast" according to the architecture they select
A requirement should come from stakeholder needs; defining it from the chosen solution reverses the direction.
المرجع: PMI-PBA Exam Content Outline, Domain 3 Analysis, Task 1 (elicit or identify requirements)
اسأل صديقًا
06On a telecom project, the product owner wants "Alert the customer by SMS when usage nears the limit" in release 1. Its implementation depends on "Real-time usage feed from the billing system", which is deferred to release 3. What is the analyst's best course of action?
سؤال تدريبي الوحدة: التحليل
أShow the dependency to decision makers and recommend putting both requirements in the same release or deferring both ✓ الإجابة الصحيحة
The dependency means the alert delivers no value without the feed; the allocation decision belongs to stakeholders once they see the impact.
بKeep the alert in release 1 and assume the team will find a workaround for the missing feed during implementation
An unfounded assumption leaves an unmanaged risk, and release 1 may ship with a feature that does not work.
جRemove the real-time feed from the list because it is a technical requirement that does not matter to the business owner
A requirement that a requested feature relies on is part of that feature's scope, and deleting it breaks the feature itself.
دSplit the alert into two requirements so that its link to the real-time feed no longer appears in the document
Hiding a dependency does not remove it; it weakens traceability and surprises the team later.
المرجع: PMI-PBA Exam Content Outline, Domain 3 Analysis, Task 2 (analyze, decompose and elaborate requirements)
اسأل صديقًا
07A business analyst at a telecom company evaluates four billing-platform requirements against four weighted criteria: business value 40%, regulatory compliance 25%, ease of implementation 20%, risk reduction 15%. Scores (1-5) in criteria order: Requirement A (5, 2, 3, 2), Requirement B (3, 5, 2, 4), Requirement C (4, 4, 3, 3), Requirement D (5, 1, 1, 3). Which requirement has the highest weighted score?
سؤال تدريبي الوحدة: التحليل
أRequirement D, 2.90
Its weighted score is 2.0 + 0.25 + 0.2 + 0.45 = 2.90, the lowest because compliance and ease of implementation score low.
بRequirement A, 3.40
Its weighted score is 2.0 + 0.5 + 0.6 + 0.3 = 3.40, below the top score.
جRequirement B, 3.45
Its weighted score is 1.2 + 1.25 + 0.4 + 0.6 = 3.45, which is 0.20 below the top score.
دRequirement C, 3.65 ✓ الإجابة الصحيحة
Its weighted score is 1.6 + 1.0 + 0.6 + 0.45 = 3.65, the highest of the four.
المرجع: PMI-PBA Exam Content Outline, Domain 3 Analysis, Task 3 (evaluate product options and capabilities)
اسأل صديقًا
08A regulator's deadline leaves four sprints, and the team's velocity is a steady 30 points per sprint. The sponsor requires delivery strictly in value order, with no skipping and no splitting of items. Backlog order: Item 1 (40 points), 2 (35), 3 (30), 4 (25), 5 (20). Which allocation should the analyst put in the release baseline?
سؤال تدريبي الوحدة: التحليل
أItems 1 to 3 (105 points), with Items 4 and 5 deferred on the backlog ✓ الإجابة الصحيحة
Capacity is 120 points (4 × 30); Items 1 to 3 total 105 and fit, while adding Item 4 exceeds capacity (130), so it stays deferred in its ranked order.
بItems 1 to 4 (130 points), with the team working overtime
130 points exceed capacity by 10, and overtime lowers quality and ignores the use of a steady velocity.
جItems 1, 2, 4, and 5 (120 points), because it uses the full capacity
The total is indeed 120 points, but skipping Item 3 to fill capacity breaks the sponsor's rule of value order with no skipping.
دItems 1, 2, 3, and 5 (125 points), assuming the team can absorb the excess
125 points exceed capacity by 5, and the assumption has no basis in the team's proven velocity.
المرجع: PMI-PBA Exam Content Outline, Domain 3 Analysis, Task 4 (allocate accepted or deferred requirements); SWEBOK Guide V4.0a, Ch. 1 §6.3 Scope Matching
اسأل صديقًا
09On a shipment management system project at a logistics company, the traceability matrix contains 120 requirements. Ten of them were formally deferred to a later phase by an approved decision. Of the remaining active requirements, 88 link to at least one test case. What is the test coverage of the active requirements?
سؤال تدريبي الوحدة: التتبع والمراقبة
أ73%
73% comes from dividing 88 by 120, which wrongly counts the deferred requirements in the denominator.
ب76%
76% matches no valid division here.
ج80% ✓ الإجابة الصحيحة
Active requirements are 120 − 10 = 110, so coverage is 88 ÷ 110 = 80%.
د88%
88% confuses the number of covered requirements with a percentage.
المرجع: PMI-PBA Exam Content Outline, Domain 4 Traceability and Monitoring, Task 1 (track requirements); SWEBOK Guide V4.0a, Ch. 1 §7.3 Requirements Tracing
اسأل صديقًا
10A government-services solution has this acceptance rule in the baseline: the solution satisfies the requirements if all 30 must-have criteria pass and at least 80% of all 50 criteria pass (30 must-have, 15 should-have, 5 could-have). Test results: 29 of 30 must-have, 14 of 15 should-have, and 3 of 5 could-have. What is the correct conclusion?
سؤال تدريبي الوحدة: التقييم
أSatisfied: the overall rate of 92% (46 of 50) is above the required 80% and no other condition is needed
The overall rate is only one condition and does not replace the first condition on must-have criteria.
بConditionally satisfied: must-have criteria passed at 96.7%, which is above the 80% required overall
The rule allows no partial pass in must-have; 96.7% does not meet its full-pass condition.
جNot satisfied: 46 of 50 (92%) exceeds 80%, but the all-must-have condition is not met ✓ الإجابة الصحيحة
The rule has two conditions together; one failed must-have criterion breaks the first condition however high the overall rate is (29+14+3=46 of 50).
دNot satisfied: should-have and could-have criteria passed 17 of 20, or 85%, below the required level
The rule sets no separate threshold for lower-priority criteria, and 17 of 20 (85%) would not fall below 80% anyway; the real reason for failure is the missed must-have criterion.
المرجع: PMI-PBA Exam Content Outline, Domain 5 Evaluation, Task 1 (validate test results against acceptance criteria)